DEVELOPMENT FEASIBILITY

Research becomes
a decision.

Pine Hill Road · Ossipee, New Hampshire · 24.8 acres

OVERALL READINESS46%Enough evidence to compare uses · field testing remains
BEST-SUPPORTED USESingle-family home88% current confidence
BEST DEVELOPMENT UPSIDESeasonal campground12–18 preliminary sites
RESEARCH REMAINING$18k–$31kDepends on selected use
EARLIEST DECISION4–8 weeksSingle-family pathway
SELECTED DEVELOPMENT PATH

Seasonal campground

Strong potential
82CURRENT CONFIDENCE
CONCEPT YIELD12–18 sitesRESEARCH TO DECISION$18k–$31kESTIMATED TIME6–10 weeksPRIMARY OPEN QUESTIONConfirm wetland crossing + septic strategy
NORTH CONCEPT AREAConcept only · not an approved plan
What we knowSite area and preliminary access can support continued evaluation. No verified constraint currently eliminates this use.
What could change the answerConfirm wetland crossing + septic strategy. Yield and cost remain conditional until the listed evidence is complete.

EVIDENCE BEHIND THE ANSWER

Facts, assumptions, and open work.

Open evidence ledger →
Zoning and dimensional reviewRural district · campground use requires planning reviewVerified
Wetland desktop screenTwo potential constraints; field boundaries pendingVerified
Topography and accessConcept access found; grades need survey confirmationVerified
Soil suitabilityTest pits and perc testing funded for Aug 19Scheduled
Utility strategyPower extension allowance received; well capacity untestedPreliminary